Upper Sanigad Hydro Electric Project (10.7 MW)

Owner : Bungal Hydro Ltd.

Installed Capacity : 10.7 MW

Total value : USD $ 9,623,705.52 (Inc. VAT) Civil Works

Major Civil Components of the Project:

          Weir : 28m x 30m x 5.3m

          Settling Basin : Length 71.7m x Width 13.2m (2Bay)

          Headrace Pipe (1.2 Dia) : 300m with concrete casing

          Headrace Tunnel:

          Length : 2812m

          Inverted D, Diameter : 2.46m

          Surge Shaft (4m dia.) : 42m (Height) open Vertical Shaft

          Penstock:

          Length : 2300m

          Diameter : 1.2-0.9m

          Powerhouse Size : 29.75m x 14.20m x 19m

 

Hydro-mechanical Details:

Total Value : USD $ 697,013.20(Inc. VAT)

No. of Gates : 17

Total Weight of Penstock : 1,455 ton

 

Transmission Line Details:

Total Value: : USD $ 135,311.58 (Ex. VAT)

          (33kV Sub-Transmission Line)

Length of TL : 8,000m